The Met Council has announced that two construction modifications of the Southwest Light Rail project in Minneapolis will likely delay the opening of the line. However, the modifications will not affect the SWLRT work calendar in Eden Prairie and elsewhere.
The January 14th announcement said that the cut-and-cover tunnel in the Kenilworth Corridor north of W. Lake Street and the protection wall between the light rail alignment and the Burlington Northern Sante Fe Railroad tracks to the northeast will require more building time.
Unforeseen soil conditions in the Kenilworth right-of-way have prompted the SWLRT project and general contractor Lunda-McCrossan Joint Venture to erect special retaining walls (secant walls) on the sides of the tunnel construction zone within which two parallel track tunnels will be constructed.
“We are taking this approach,” said the Met Council announcement, “out of an abundance of caution to protect the foundations of adjacent buildings.”
The freight tracks used by Twin Cities & Western Railroad trains have already been shifted to the north edge of the tunnel’s construction area.
Passenger service on what will be known as The Green Line Extension, the project says, might be pushed ahead from 2023 to 2024. Work on the SWLRT project in Eden Prairie, Minnetonka, Hopkins, St. Louis Park and elsewhere in Minneapolis, says the Met Council will continue as anticipated.
For more SWLRT construction progress in Eden Prairie in 2020 see EPLN’s review here.
Read the full January 14, 2921 SWLRT announcement on the modifications here.
Note: EPLN reporter Jeff Strate served on the SWLRT Community Advisory Committee as an at-large member, February 2015 – February 2017.
Comments
We offer several ways for our readers to provide feedback. Your comments are welcome on our social media posts (Facebook, X, Instagram, Threads, and LinkedIn). We also encourage Letters to the Editor; submission guidelines can be found on our Contact Us page. If you believe this story has an error or you would like to get in touch with the author, please connect with us.